Design Development vs Construction Documents: What Changes

Design development (DD) decides how a building will be built and how it will operate, while construction documents (CD) turn those decisions into the complete, coordinated drawings and specifications that a municipality reviews for a permit and a contractor prices and builds from. For a developer, contractor, property manager or architect, the practical difference is that DD is the last phase in which changes are cheap, and CD is the phase in which the project becomes a contract.

This article explains each phase in the way Canadian practice guides describe it, shows how schematic design fits before them, and sets out what the mechanical and electrical engineer contributes at each stage. Our own engineering work in Ontario sits in exactly this transition, so the focus is on what must be settled before drawings are released for permit and tender.

Futuregenconsulting
Coordinate MEP Design Through Every Phase
FutureGen Consulting provides mechanical and electrical engineering design for Ontario residential and commercial projects.

Visit

TL;DR

  • Schematic design answers “what will be built”; design development answers “how”; construction documents record it in a form that can be permitted, tendered and built.
  • DD fixes dimensions, systems and outline specifications and requires approval by the owner. CD adds complete drawings, full specifications and schedules.
  • Mechanical and electrical systems are sized and coordinated in DD; in CD they become detailed, stamped, code-checked documents.
  • Late changes cost far more than early ones, so coordination should run through DD and not wait for the CD set.
  • Cost estimates tighten at each phase, ending with a pre-tender estimate based on the CD set.

Table of Contents

Where the two phases sit in the design sequence

Canadian practice describes a staged sequence. After pre-design (programming, site documentation, budget), the consultant team works through schematic design, design development and construction documents, followed by bidding or tendering and construction administration. A Canadian introductory construction course lays out the same order and notes that the broad cost estimate of schematic design is refined in design development and finalized for the construction documents.

The federal Documentation and Deliverables Manual published by Public Services and Procurement Canada in 2023 gives the cleanest summary of the split. Schematic design resolves the client’s requirements into physical form, describing what will be built. Design development refines that scheme to determine how it is built and will operate. Construction documents become the consultant’s primary reference for administering the construction contract, capturing the project objectives for cost, time, sustainability, durability and accessibility.

Schematic design versus design development

Owners who search for the difference between schematic design and design development are usually asking where concept ends and engineering begins. The Royal Architectural Institute of Canada (RAIC) states in its chapter on schematic design that schematic design transforms pre-design results into a concept of what will be built, and that how it will be built is explored later in design development.

In practice, the schematic deliverables are conceptual. RAIC lists a site plan showing location and circulation, block plans showing adjacencies, sections, outline elevations showing massing, concept sketches or renderings and 3D massing models. The accompanying report records the probable construction cost, code and zoning status, a preliminary schedule and short descriptions of the structural, mechanical and electrical systems, including vertical shafts. At this stage a mechanical description may be a paragraph and a shaft allowance; nothing is yet sized.

The RAIC also sets a gate before design development begins: the architect must obtain formal written client approval of the schematic design. That approval is the owner’s last easy opportunity to change the scope, area or program without redrawing coordinated work.

Schematic design versus design development

What design development settles

Design development takes the approved concept and fixes it. The RAIC chapter on design development lists the tasks: preparing and coordinating all architectural, structural, mechanical and electrical designs, writing outline specifications, running preliminary energy or daylight modelling where it is included, developing construction phasing scenarios, setting a regulatory compliance strategy with reviews by the authorities having jurisdiction (AHJ, the bodies that enforce the codes locally), preparing presentation documents, updating the construction cost estimate and updating the design, construction documents and construction schedules.

The Canadian course material describes the same phase as the point where dimensions are fixed, structural, mechanical and electrical systems are selected, outline specifications are written and a more detailed estimate is produced. The American Institute of Architects (AIA) describes the same step for US practice: floor plans, sections and elevations with full dimensions, door and window details and outline material specifications, concluding with formal owner approval. The terminology is consistent across the border, though Canadian projects work against the National Building Code and, in Ontario, the Ontario Building Code and the Ontario Electrical Safety Code.

What the owner should expect to approve

For larger projects, DD documents typically consist of three components: drawings, outline specifications and a design report, according to the RAIC. A useful test of a DD package is whether each building system has a chosen type, a rough size and a location:

  • the electrical service entrance, main distribution equipment and electrical room size;
  • the heating, ventilating and air-conditioning (HVAC) system type, plant location, shafts and ceiling space;
  • the plumbing riser strategy and any fire protection water supply;
  • the fire alarm and life safety approach, tied to the compliance strategy agreed with the AHJ.

If these items remain open at the end of DD, they will be resolved during CD under schedule pressure, which is when conflicts with structure and architecture appear.

What construction documents contain

Construction documents are the set from which the project is permitted, tendered and built. The RAIC chapter on construction documents describes them as drawings showing building elements and their interconnections, specifications describing material, quality, workmanship and acceptance criteria, schedules and complementary documents, all detailed enough to direct the builder. The same chapter notes that they are authored by design professionals, are required in Canada for almost any project that uses an architect, and form part of the construction contract or tender documents. Typical schedules include building code compliance, doors, finishes, electrical panel configuration and air-handling unit details.

The Ontario Association of Architects’ standard form of contract defines construction documents as the drawings, specifications and other documents appropriate to the project’s size and complexity, describing the architectural and, where applicable, structural, mechanical and electrical systems and materials in detail for construction, enlargement or alteration.

Permit requirements shape the set

Municipal building departments set minimums for what must be submitted. The Township of Adjala-Tosorontio, for example, requires complete construction drawings, including floor plans, elevations, sections, details and a roof plan, a fully dimensioned site plan and engineered drawings where required, and the approved set must be kept on site for trades and inspections. Port Hope’s building permit guide requires drawings to scale, distinguishes existing from proposed construction and specifies digital submission as flattened PDF. Local requirements vary, so the municipal building department’s current guide governs. Our guide to Ontario building permit requirements covers the submission side in more detail.

Design development and construction documents compared

Aspect Design development Construction documents
Central question How will it be built and operate? What exactly is to be built, and to what standard?
Detail level Fixed dimensions, selected systems, outline specifications Complete coordinated drawings, full specifications, schedules
MEP content System types, rough sizing, equipment and shaft locations Detailed layouts, equipment schedules, single-line diagrams, riser diagrams, specifications
Regulatory role Compliance strategy and reviews with the AHJ Permit submission, tender and construction reference
Cost estimate Updated, more detailed estimate Final pre-tender estimate
Owner action Formal approval before CD starts Release for permit and tender
Cost of change Moderate High, and higher again once tendered

How the engineer’s work moves from DD to CD

For a mechanical and electrical engineering firm, the two phases ask different questions. In DD the engineer establishes design criteria, confirms code requirements, selects systems and sizes them well enough to reserve space and budget. In CD the engineer produces the detailed documents that an electrical or mechanical contractor will price and install from, and that a building official will review.

The Ontario Association of Architects’ practice tip on coordination of consultants frames this division. In the schematic and DD phases, teams establish design criteria with consultants, review alternatives, confirm program and code requirements, integrate outline specifications, check layout consistency and monitor estimates. During CD, teams review the detailed documents for compliance, integrate specifications, have each consultant check their own coordination, resolve conflicts and update the cost estimate.

Typical MEP outputs by phase

In design development, electrical engineering usually fixes the load assumptions, the service size and the main distribution concept, while mechanical engineering fixes the HVAC approach and the plumbing and fire protection strategy. In the construction documents, these become fully dimensioned drawings, schedules and specifications. Our offer pages describe the corresponding services: HVAC system design, plumbing system design, fire protection and fire alarm design and power distribution design.

MEP outputs compared across design phases

Two points deserve attention before the CD set is issued. First, load calculations should be complete: an HVAC or electrical design carried into CD on assumed loads produces equipment schedules that change later. Our article on HVAC design in Ontario explains why this step carries so much weight. Second, fire alarm and life safety design should follow the compliance strategy agreed in DD, as covered in our guide to fire alarm system design in Ontario.

Cost estimates at each phase

Each phase supports a more reliable estimate. The phase table in the course material assigns a Class D or concept estimate to schematic design, Class C or B to design development, and Class A or a pre-tender estimate to construction documents. Class labels differ between organizations, so the useful principle is the direction: the more complete the documents, the narrower the range.

For an owner, this means that a budget confirmed at the end of DD should be tested against the electrical and mechanical scope specifically, since these trades carry equipment with long lead times and large cost swings. A separate estimate of the electrical scope, such as our electrical construction cost estimation, gives the owner a figure to compare against the budget before the drawings are fixed.

Coordination: where most late problems start

The Canadian course material explains the typical failure. Architectural plans, structural drawings and mechanical and electrical drawings must agree, and when they do not, the conflicts are physical: a duct through a beam, or a door swinging into a column. A document review before construction finds such problems while they are still inexpensive to fix, and building information modelling (BIM) clash detection makes the search more systematic.

The RAIC states that coordination must not wait until the construction documents are nearly complete. It should run through the entire design process, because a well-integrated design limits delays during CD production and late revisions are expensive for the client, architect and subconsultants. The RAIC also notes that the coordinating professional, the architect acting as prime consultant, plans the production of the CD set: which drawings are needed, how production is organized, who handles each coordination task and what the milestones are.

Some public programs formalize the milestones. The DASH Projects BIM Requirements, published in March 2026, call for design models in native and IFC 4.X+ formats with 2D deliverables at schematic design, design development, 50% and 100% construction documents, issued for tender and issued for construction, with the BIM execution plan starting at schematic design.

A pre-release checklist for the CD set

Before the set is released for permit or tender, owners and project managers can ask the design team to confirm:

  1. Every system selected in DD appears in the drawings, with the same equipment sizes and room dimensions.
  2. Mechanical and electrical rooms, shafts and ceiling zones are shown on the architectural and structural drawings.
  3. Specifications agree with drawings, and the schedules (equipment, panels, doors, finishes) match both.
  4. The code compliance items agreed with the AHJ in DD are carried into the documents.
  5. The cost estimate has been updated against the final set.

The RAIC’s management checklists include separate task lists before and during DD and before and during CD, and are a sound base for the architect’s own process. Once documents are issued, disciplined revision control matters; see our article on construction document control and, for changes after award, our overview of construction change orders.

Why skipping pre-design and DD discipline costs money

The RAIC warns that starting schematic design without completing pre-design risks delay, cost overruns and design deficiencies. It requires the client to supply a functional program (spatial requirements, budget, schedule, sustainability goals) and full site documentation, including surveys, zoning considerations and subsurface reports, before schematic design starts. The same logic applies to engineering: an owner who confirms the electrical service capacity, the intended tenants or equipment and any EV charging or solar provisions during DD avoids redesign in CD. For projects that include charging, the EV charger infrastructure design scope is best defined at this stage, because panel capacity and conduit routes are set by then.

Engineering support through design development and construction documents

FutureGen Consulting Inc. provides mechanical, electrical and plumbing engineering design for residential and commercial projects in Ontario, with over 30 years of experience. The work covers power distribution, HVAC, plumbing, sprinkler, fire alarm and life safety design, emergency power, solar and EV charger infrastructure, construction reviews and detailed electrical construction cost estimation, delivered as permit-ready, engineer-stamped drawings that address building code compliance.

Owners and architects who bring the engineer in during design development, and not at the start of construction documents, give the team time to resolve loads, space and compliance before drawings are issued. Project scope and fees are set per project; the services page lists the full range, and the home page is the place to begin an enquiry.

Futuregenconsulting

For renovation work, our construction review service and our guide to as-built drawings address the stages that follow the issued documents.

Our perspective

In our experience as an engineering firm, the most useful question to ask at the end of design development is not whether the drawings look complete, but whether every electrical and mechanical decision has an owner and a location. A panel without a room, a rooftop unit without a structural allowance or a fire alarm approach without an agreed compliance strategy are all items that look small in DD and become change orders later.

We design for this transition. Our stamped drawings are prepared for permit review and building code compliance, and our approach is built around flexibility and end-to-end project support, from design through construction review. We recommend that owners, developers and architects involve the MEP engineer when the design is still being developed, so that load calculations, equipment sizing and code strategy are settled before the construction documents are produced.

A construction document set is a contract instrument. We would rather the electrical and mechanical scope be fixed in a set that the contractor can price once than clarified repeatedly during construction.

Sanjay

FAQ

What is the difference between DD and CD drawings?

DD drawings show the selected design with fixed dimensions, system types and outline specifications, and they are used for owner approval and coordination. CD drawings are the complete, detailed set with full specifications and schedules, used for permit, tender and construction. DD sets what the building is; CD instructs how the contractor builds it.

Who is responsible for coordinating the consultants during these phases?

On most projects with an architect, the architect acts as the coordinating professional, or prime consultant, and plans the production and coordination of the set, according to the RAIC. Each consultant, including the mechanical and electrical engineer, also checks the coordination of its own drawings during CD. The RAIC notes that these coordination duties should be stated clearly in the services contract.

Can design changes be made after construction documents are issued?

Changes can be made, but they are costlier, because drawings, specifications, schedules and the cost estimate all need revising, and a tendered project adds contract consequences. This is why the RAIC and the OAA stress coordination and approval during design development. Post-award changes are usually handled through a formal change order process.

Is design development the same as schematic design?

No. Schematic design establishes the concept, the layout and massing, and a probable cost, and answers what will be built. Design development takes that approved concept further, fixing dimensions and systems and answering how it will be built and operate, with an updated estimate.