A load bank connection is designed correctly when the generator can be loaded to its full rated output through a dedicated, protected, lockable and code-compliant point, without disturbing the building’s normal supply and without improvised cable work on the day of the test. That point is a design decision made on the single-line diagram, not a field decision made at the generator. In Ontario, a stamped design that shows the connection cabinet, conductor sizing, protective devices and isolation sequence also gives the electrical inspection and permit process something concrete to review. Our power distribution and emergency power design work covers this connection as part of the electrical package.
This article is written for developers, contractors, architects, property managers and building owners who must specify or approve the connection, not for the technician who operates the load bank.
TL;DR
- Decide early whether the connection is temporary (a portable bank connected through a cabinet with quick-connect receptacles) or permanent (a fixed bank on armored or conduit-run cable). The choice drives hardware, space and cost.
- Size the connection for the generator’s full kVA current at 0.8 power factor, not only for the kW of a resistive bank. Include temperature and bundling corrections.
- Put the connection behind a properly rated, lockable breaker, preferably interlocked with the service or transfer arrangement, so the building is never fed from the wrong source.
- Specify the cabinet to CSA C22.2 requirements, with short-circuit rating, grounding, heat and weather exposure addressed on the drawings.
- Design to the Ontario Electrical Safety Code or the Canadian Electrical Code as adopted where the site is, and to CSA C282 for emergency power.
Table of Contents
- What a load bank connection has to accomplish
- Temporary or permanent: the first design decision
- Sizing the connection: current, not just kilowatts
- The load bank connection cabinet
- Connecting without compromising the building
- Grounding, bonding, heat and access
- Canadian code framework
- Design steps, in order
- How we help on load bank connections
- Our perspective
- Frequently asked questions
- Sources
What a load bank connection has to accomplish
A generator that only ever carries a small share of its rating is never proven at its rated output. A load bank supplies an adjustable, known electrical load so the set can be run at its rated output and the result recorded. The connection is the electrical path between the generator (or the emergency distribution) and that bank.
The design therefore has four jobs:
- Carry the full test current continuously and without overheating, including the reactive portion when a combined resistive-reactive bank is used.
- Protect the conductors and the generator with an overcurrent device that is correctly rated and that can be locked open.
- Isolate the test from the building load, or coordinate it with the building load, so a utility failure during the test does not leave occupants without power.
- Be repeatable: the same cabinet and procedure should serve the annual or monthly tests for the life of the building.
CSA C282:24, the national standard for emergency electrical power supply for buildings, sets the monthly generator test minimum at 30% load and adds testing requirements for automatic load management systems. The same standard covers the design, installation, operation, maintenance and testing of emergency generator sets where the National Building Code of Canada requires them, and, with CSA Z32, essential electrical systems in health care facilities. A building that cannot reach those test levels with its normal load needs a connection point designed for a bank. For the testing procedure itself, see our generator load bank testing compliance guide.
Temporary or permanent: the first design decision
The distinction between a portable bank brought to site and a bank installed permanently changes the connection hardware. A portable application typically uses quick-connect receptacles so the crew can connect quickly, while a permanent installation uses code-specified cable directly to the bank; quick-connects are generally not appropriate for permanent installations. The table summarizes how the two approaches differ at the design stage.
| Design question | Temporary (portable bank) | Permanent (fixed bank) |
|---|---|---|
| Connection hardware | Cabinet with cam-type receptacles or lugs | Fixed conductors in conduit or armored cable to the bank |
| Where the bank sits | Anywhere the truck can park, within cable reach | A designed pad, roof or enclosure with airflow |
| Typical owner | Buildings with annual or occasional tests | Data centres, hospitals, plants with frequent testing |
| Design burden | Cabinet, parking position, cable routing | Cabinet, structure, ventilation, controls, protection |
| Recurring cost | Bank hire for each test | Maintenance of owned equipment |
A third arrangement sits between the two: a permanent bank with controls that add load automatically when the building load is low, so the generator never runs lightly loaded. That is a controls and protection design question as much as a connection question, and it overlaps with generator load shedding design.
For most commercial and multi-residential buildings the temporary arrangement is the practical answer. The connection cabinet is permanent; the bank is not. Our temporary power design work uses the same inlet principles.
Sizing the connection: current, not just kilowatts
Load banks are ordered by kW, generators are rated in kVA, and the connection must carry amperes. Confusing the three is the most common sizing error on a first design.
A generator is typically rated at 0.8 power factor. A purely resistive bank operates at unity power factor, so it loads the engine fully but draws only about 80% of the alternator’s rated current. When the commissioning requirement calls for fully loading the alternator, a resistive-reactive bank is needed, and the connection must be sized for the higher current.
Worked example (our own arithmetic, three-phase): a 1,000 kVA generator at 0.8 power factor has an engine rating of 800 kW.
| Voltage | Full alternator current (1,000 kVA) | Resistive test only (800 kW, unity PF) |
|---|---|---|
| 600 V | about 962 A | about 770 A |
| 480 V | about 1,203 A | about 962 A |
The design current is the larger figure: the connection, the cables, the breaker and the cabinet should be rated for the full alternator current, because the test requirements can change from a resistive test to a combined test over the building’s life. A resistive-reactive bank at 0.8 power factor for this generator would also absorb 600 kVAr.
Voltage, phase and tolerances
The bank voltage must match the generator voltage. Typical Canadian commercial systems are 208 V, 480 V or 600 V three-phase; the design should state which. Load bank manufacturers state standard tolerances of plus or minus 5% on power and frequency, with a short-duration allowance on voltage, and the same manual warns that the three-phase and neutral sequence must be correct, since connecting a phase to neutral damages the bank. That is a reason to colour-code and label the cabinet terminals on the drawings, so that phase rotation is never in question when a visiting crew connects.
Conductors, derating and voltage drop
Test cables are usually several large single-conductor cables per phase. Their capacity falls with ambient temperature and with the number of cables bundled together. A manufacturer’s application paper on a 2 MW generator shows that ambient and bundling corrections reduce the capacity of eight large cables from 3,800 A to 2,340 A, and concludes that generator connection boxes are often undersized because they must accommodate several large cable entries. Apply the correction tables of the Canadian Electrical Code, or of the Ontario Electrical Safety Code for Ontario sites, to the actual installation conditions, then check voltage drop over the real distance between the cabinet and the bank’s parking position.
Voltage drop matters for a test more than for normal service. Because kW varies with the square of voltage, a low voltage at the bank terminals reduces the delivered kW, and the difference is dissipated as heat in the cables. A connection designed with short, direct runs and a bank position fixed on the drawings avoids this.
Bank size relative to the generator
A bank sized exactly to the generator leaves no margin and no ability to hold the 75% step without running the bank at its limit. Sizing the bank to at least 80% of generator kW is a common recommendation, with step resolution fine enough to hit the 25, 50, 75 and 100% levels. The connection, however, should always be designed for the generator’s full output, whatever bank is hired.
The load bank connection cabinet
The connection cabinet is the permanent piece of equipment that makes the whole arrangement work. It is a small switchboard, and it should be specified like one. Our guide to switchboard versus switchgear in Canada explains when the voltage and the fault level push the specification toward switchgear.
What the specification should state
A generator quick-connect switchboard specification published for the Canadian market, for example, requires the assembly to be designed, manufactured and tested to CSA C22.2 No. 31 and rated for short-circuit withstand up to 65 kA at 600 V or 200 kA at 208 V. The same document asks for submittals that list the short-circuit rating, voltage, continuous current, component interrupting ratings and lug sizes. Our specification checklist follows the same logic:
- Source and bank terminals for phases A, B, C, neutral where used, and ground.
- Main breaker or disconnect for the connection, lockable, sized for the full alternator current, with interrupting rating at least equal to the available fault current at that point.
- Interlocking so the connection cannot be energized from the wrong source. A Canadian-market quick-connect design key-interlocks a CSA-approved breaker with the service disconnect, and ratings are offered up to 2,500 A.
- Receptacles or lugs. The same switchboard specification provides both mechanical lugs and cam-type receptacles, with each single-pole receptacle rated at least 400 A at 90 °C and multiple receptacles per phase above that current.
- Enclosure rating suited to the location. A Canadian manufacturer’s quick-connect panels are offered with enclosure ratings up to 4X, current ratings up to 4,000 A and Canadian voltage configurations including 600/347 V, certified to CSA C22.2 standards.
- Labelling of phase sequence, voltage, maximum current and the isolation procedure on the cabinet door.
The point of these ratings is not the product; it is that the cabinet is engineered once, for the worst case, and then used safely for decades.
Layout and cable entry
Place the cabinet where a truck-mounted or trailer-mounted bank can park within cable reach, outside the building where possible, so that heavy cables are not routed through doorways or corridors. Provide a clear working space, a drain or protected entry, and a physical barrier or bollard if vehicles will be nearby. Leave room for the bank’s own connection chamber, because one manufacturer’s manual notes that all cables pass through the same opening into the chamber and the doors must be closed once the cables are fitted. Cables with a minimum bend radius need a straight approach, not a tight corner at the cabinet.
Connecting without compromising the building
Two arrangements keep the building safe during the test.
The first is a dedicated bank breaker on the generator bus or on the emergency distribution, so the load bank is connected in parallel with the building load. This is generally better than disconnecting the building’s feeder cables to connect the bank, because a utility failure mid-test would then leave the building without a path to the generator. A dedicated connection also removes the repeated disconnecting and reconnecting of building cables, which is a source of damage and error.
The second is a switching arrangement in which the bank connection point is fed through the transfer equipment, so that a trip signal opens the bank breaker if utility power is lost and the generator is immediately redirected to the building. This needs coordination with the automatic transfer switch controls. It is a design item for the electrical engineer, not something to leave to the testing crew.
On either arrangement, the designer should provide a written isolation sequence on the drawings: breakers off, source locked out and tagged out, absence of voltage verified with a properly rated instrument, then connection. Reversing that order is how backfeed and shock injuries occur.
Grounding, bonding, heat and access
Grounding and bonding. The equipment grounding conductor should be terminated first, lugs torqued to the manufacturer’s values, and metallic conduit bonded to the enclosure. The bank and the cabinet must share a bonding path with the generator and the building system. Our grounding and bonding guide sets out the Canadian approach, including how separately derived systems and neutral bonding are shown on the single-line diagram.
Heat. A bank turns every kilowatt of test load into heat; a 1,000 kW bank discharges roughly 1 MW of heat. The bank’s position must allow free intake and exhaust, away from building air intakes, windows and combustible materials, and never in an enclosed parking structure without engineered ventilation. If the building’s mechanical design is part of the same project, our team coordinates the bank’s exhaust path with the building’s HVAC intakes.
Weather and winter. Canadian sites are tested in cold, snow and rain. Specify an outdoor-rated enclosure, a drained base, and a cabinet door that can be operated safely with gloves on.
Access and security. The cabinet should be lockable, with the bank breaker able to be locked open. Access paths should suit a truck and a crane if a large unit is used.
Canadian code framework
The design should cite Canadian codes only, and the applicable edition depends on the province.
- Ontario. The 2024 Ontario Electrical Safety Code (29th edition) took effect on 1 May 2025 and includes plan-review submission requirements for stand-alone electric power generating equipment and systems. A generator with a permanent load bank connection should therefore be treated as a plan-review item, and the submission should include the connection cabinet, conductors and protection.
- Canadian Electrical Code. Other provinces adopt the CEC with their own amendments. The 2024 edition, for example, added GFCI requirements for outdoor or damp locations in Section 66, as adopted in Nova Scotia. For Alberta projects, we confirm the edition and amendments the authority having jurisdiction applies at the time of design.
- CSA C282:24 for emergency power supply, and CSA Z32 for health care essential electrical systems.
- CSA C22.2 standards for the equipment, such as switchboards and receptacles.
- National Building Code of Canada where emergency power is required for life-safety systems.
The design drawings should name the edition used, and the short-circuit and coordination calculations behind them should be available on request. Our power system studies provide the fault-current and coordination analysis that the cabinet rating depends on, and our electrical load calculation guide shows how the building load and generator capacity are established.
Design steps, in order
- Confirm the generator data: kVA, kW, voltage, phase, power factor, any derating for altitude or temperature, and available fault current at the generator terminals. Errors here carry through everything else.
- Define the test requirement: resistive only or combined, test levels, duration, and how often. This sets the bank type and the design current.
- Choose temporary or permanent arrangement and the bank’s parking or pad position, with heat and airflow considered.
- Size conductors and protection for the full alternator current, with temperature and bundling corrections and a voltage-drop check.
- Specify the cabinet: CSA C22.2 listing, short-circuit rating, lockable breaker, interlock, receptacles or lugs, enclosure type and labelling.
- Coordinate with transfer equipment and controls, including any load management system that CSA C282:24 now requires to be tested.
- Document the isolation and connection sequence on the drawings.
- Prepare the permit submission and carry out a construction review so the installed cabinet matches the design before the first test.
At each of these steps, the work that most often costs a project time is the coordination: the generator supplier’s data, the transfer switch, the short-circuit rating and the permit submission all have to agree. Our engineers produce the permit-ready, stamped drawings for the full set, and construction review confirms the installation.
How we help on load bank connections
FutureGen Consulting designs the electrical side of emergency and standby power for residential and commercial projects in Ontario, including power distribution, emergency power, temporary power, power system studies and construction review, with permit-ready engineer-stamped drawings and building code compliance. A load bank connection can be added to a new generator design or retrofitted to an existing building as a defined package: cabinet, conductors, protection, isolation sequence and permit documentation.
If you are planning a generator installation or a renovation that adds emergency power, contact us through our services page and describe the generator and the building.
For larger projects, our power distribution design guide explains how the connection fits the wider electrical system.
Our perspective
The most expensive load bank connection is the one that was never designed. We see the pattern described in industry guidance repeatedly: a generator is installed, the building passes its commissioning, and the first annual test becomes a field improvisation of cables, borrowed breakers and a disconnected feeder.
Our position is that the connection belongs on the first revision of the single-line diagram. It is a small item on the drawings and a large item on the day of the test. A cabinet sized for the full alternator current, with a lockable interlocked breaker and a labelled isolation sequence, costs little to include during design and a great deal to retrofit.
We design power distribution, emergency power, temporary power and power system studies together, so the fault-current rating of the cabinet, the transfer switch controls and the permit submission are consistent from the start. That is the benefit of one engineering team holding the whole electrical package, with stamped drawings and a construction review at the end.
Sanjay
Frequently asked questions
Can a load bank be connected to an existing generator without a dedicated cabinet?
It is possible, but it usually means disconnecting building cables or tapping a live bus, which adds risk and downtime. A dedicated connection point designed into the electrical system removes both. For an existing building, we can add one as a retrofit with permit drawings.
Is a resistive load bank enough for the test?
A resistive bank loads the engine to its kW rating but draws only about 80% of the alternator’s rated current at a 0.8 power factor generator. Where the commissioning or the standard calls for the alternator to be fully loaded, a resistive-reactive bank is used, and the connection must be sized for the higher current.
What load level does CSA C282:24 require for monthly testing?
The 2024 edition restores the minimum monthly generator test load to 30% and adds testing requirements for automatic load management systems. Annual and acceptance tests are normally carried out at higher load steps, which is why the connection is designed for the full output.
Does a permanent load bank connection need an electrical permit in Ontario?
Stand-alone generating equipment and systems are subject to plan review under the 2024 Ontario Electrical Safety Code, effective 1 May 2025. The connection should therefore be included in the engineered submission. The Electrical Safety Authority confirms what each project must submit.
Sources
- CSA C282:24 Emergency electrical power supply for buildings
- Ontario Electrical Safety Code, Electrical Safety Authority
- Adoption of the 2024 Canadian Electrical Code, Part I, safety bulletin
- Generator quick-connect switchboard specification, CSA C22.2 No. 31
- Generator quick-connect product sheet
- Quick connect panels, Canadian product page
- Load bank installation and operation manual
- Generator connection design application paper